WATER AND IRRIGATION
Environmental and Social Impact Assessment for the proposed Rehabilitation, Upgrading and Expansion of Dowa Town Water Supply Scheme and Construction of Sanitation Facilities.
Client: Central Region Water Board
Policies Used : MALAWI
Completion Date: 2023-June 2025
-
Reviewing project designs and relevant literature,
-
Conducting public consultations
-
Assessing the proposed sanitation investment options and designs; and proposing alternatives
-
Assessing the positive and negative impacts of the proposed project;
-
Proposing feasible mitigation and enhancement measures;
-
Reviewing and proposing a Grievance Redress Mechanism (GRM) of the project
-
Preparation of Environmental and Social Scoping Reports
-
Preparation of Environmental and Social Impact Assessment Report; and
-
Preparation of costed Environmental and Social Management Plans and Environmental and Social Monitoring Plans.
Preparation of detailed design, tendering assistance and construction supervision of Nkhatabay water supply and works including baseline survey-Phase II
Client: Northern Region Water Board
Policies Used : Malawi & AfDB
Completion Date: 2020-2023
-
Reviewing relevant literature
-
Conducting public consultations
-
Assessing the proposed building designs and proposing alternatives
-
Assessing the positive and negative impacts of the proposed project;
-
Proposing feasible mitigation and enhancement measures;
-
Reviewing the Grievance Redress Mechanism (GRM) of the project and proposing a GRM for the sub-project
-
Preparation of Environmental and Social Impact Assessment Report; and
-
Preparation of costed Environmental and Social Management Plans and Environmental and Social Monitoring Plans.
Environmental and Social Impact Assessment for Extension of Mangochi Potable Water Supply Scheme
Client: Southern Region Water Board
Policies Used : MALAWI
Completion Date:
-
Reviewing project designs and relevant literature,
-
Conducting public consultations
-
Assessing the proposed sanitation investment options and designs; and proposing alternatives
-
Assessing the positive and negative impacts of the proposed project;
-
Proposing feasible mitigation and enhancement measures;
-
Preparation of Environmental and Social Impact Assessment Report; and
-
Preparation of costed Environmental and Social Management Plans and Environmental and Social Monitoring Plans.
Environmental and Social Impact Assessment for Upgrading and Extension of Liwonde Water Supply Scheme; including Balaka Town
Client: Southern Region Water Board
Policies Used : MALAWI
Completion Date:
-
Reviewing project designs and relevant literature,
-
Conducting public consultations
-
Assessing the proposed sanitation investment options and designs; and proposing alternatives
-
Assessing the positive and negative impacts of the proposed project;
-
Proposing feasible mitigation and enhancement measures;
-
Preparation of Environmental and Social Impact Assessment Report; and
-
Preparation of costed Environmental and Social Management Plans and Environmental and Social Monitoring Plans.
Preparation of detailed design, tendering assistance and construction supervision of Nkhatabay water supply and works including baseline survey-Phase I
Client: Northern Region Water Board
Policies Used : MALAWI & AfDB
Completion Date:
-
Prepared detailed design of water supply system
-
Prepared detailed design of liquid and solid waste management facilities and public toilets
-
Tendering assistance
Preparation of sanitation and hygiene investment plan for Nkhatabay Town
Client: Northern Region Water Board
Policies Used : Malawi & AfDB
Completion Date: March 2019-2020
-
Conducted baseline assessment
-
Developed alternative option and recommended means of collecting, treating and disposing of sewered wastewater from the area.
-
Conducted environmental and social impact screening in accordance with the ESMF, RPF, financier’s guidelines and environmental policy as well as National Environmental Action Plan Guidelines and procedures of the Government of the Republic of Malawi.
-
Conducted institution analysis
-
Conducted an analysis of how the project will affect women and children
-
Conducted a situational analysis
Construction of network and house connections in the City of Malanje- Angola
Client: Republic of Angola (National Directorate of Water Supply and Sanitation
Policies Used : Angola & World Bank
Completion Date:
-
Reviewed environmental and social safeguard documents to ensure that contractor is complying to them; and
-
Assessed Gender-Based Violence (GBV) and sexual harassment (SH) concerns at the work site.
Environmental and Social Impact Assessment for 2 River Intakes
Client: Northern Region Water Board
Policies Used : MALAWI
Completion Date:
-
Reviewing project designs and relevant literature,
-
Conducting public consultations
-
Assessing the proposed sanitation investment options and designs; and proposing alternatives
-
Assessing the positive and negative impacts of the proposed project;
-
Proposing feasible mitigation and enhancement measures;
-
Preparation of Environmental and Social Impact Assessment Report; and
-
Preparation of costed Environmental and Social Management Plans and Environmental and Social Monitoring Plans.
Environmental and social impact assessment for Lunyangwa dam raising
Client: Northern Region Water Board
Policies Used : MALAWI
Completion Date:
-
Reviewed project designs and relevant literature,
-
Conducted public consultations
-
Assessed the positive and negative impacts of the proposed project;
-
Proposed feasible mitigation and enhancement measures;
-
Prepared Environmental and Social Management Plans and Environmental and Social Monitoring Plans;
-
Determined costs for implementing the recommended mitigation and monitoring measures
Environmental and Social Impact Assessment for the Proposed Rehabilitation, Upgrading and Expansion Works for Karonga Water Supply Scheme
Client: Northern Region Water Board
Policies Used : MALAWI
Completion Date:
-
Reviewing project designs and relevant literature,
-
Conducting public consultations
-
Assessing the proposed water supply designs and proposing alternatives
-
Assessing the positive and negative impacts of the proposed project;
-
Proposing feasible mitigation and enhancement measures;
-
Preparation of Environmental and Social Impact Assessment Report; and
-
Preparation of costed Environmental and Social Management Plans and Environmental and Social Monitoring Plans.